Onsite Piling
In 17 months, RCF installed the pile foundation and performed the civil works for the major and heaviest items in the Dangote refinery, including the Main Reactor and the Unicracking Unit.
The team installed 8,230 driven cast in-situ piles, 500 mm in diameter, at depths of 12, 21, 25 and 28 m.
Tank Pad Foundations and Dyke Wall
Twelve tank pad foundations for tanks 92 m in diameter, which the old site describes as among the biggest crude tanks in the world, with the ring beam, the pavement and the 42 km dyke wall of the refinery tank farm.
Road Works
Strengthening and reinforcement of the refinery's internal roads and approaches, using 405,042 m³ of sand and 73,076 m³ of stone base.

























